(a) Plan development.
The planning must meet the following requirements:
-
(1) The plan must be developed by a qualified person.
-
(2) The plan must be designed to ensure that the requirements of this subpart are met.
-
(3) Where the qualified person determines that engineering expertise is needed for the planning, the employer must ensure that it is provided.
-
Plan implementation.
-
(1) The multiple-crane/derrick lift must be directed by a person who meets the criteria for both a competent person and a qualified person, or by a competent person who is assisted by one or more qualified persons (lift director).
-
(2) The lift director must review the plan in a meeting with all workers who will be involved with the operation.